Stage two of the Greens Replacement Program is well under with eight green complexes under construction. Schedule of works for greens 12, 13, 14, and 16. September 4 - 8: - Finish preparing green complexes on holes 12 and 13 ready for grassing.
- The
green surrounds including bunker edges on holes 12, 13, 14 and 16 will be
sodded with Santa ana couch grass.
September 11 - 15: -
Seed first 4
greens including the new greens turf nursery.
- Finish sodding rough
areas on these green complexes.
- Tidy up areas.
- Planting of native
grasses and ground covers at the rear of the 14th green and
right of the 16th fairway bunker.
Schedule of works for greens 2, 3, 5, and 6.
September 4 - 8: -
OCM to sign off with the
Club on these green complexes.
- Reticulation to be
installed Sep 6-12.
- Construct bunker edges.
September 11 - 15: -
Fumigation of these
green complexes.
See a few photos of the work in progress. |